SC
3

Notifications

Design check on hold

ANU Solar tub — roll-hoop pitch 7.5 mm short. Cutting blocked until resolved.

Invoice overdue

SC-INV-10680 (Tilton) is 19 days overdue — $7,480.

5 materials below reorder

Prepreg twill, forged tow, Nomex 6mm, vac bag film, threaded pucks.

Job due soon

SC-J-26-0146 (Evo bonnet) due 18 Sep — in QA.

Prepreg out-life

Film adhesive LOT-AD-2555 expires 18 Oct — use or quarantine.

Batch certified

SC-J-26-0169 complete — 12 strakes serialised, COC issued.

PO received

SC-PO-26-044 received — bagging consumables back in stock.

Quote accepted

Xtreme Motorsport accepted SC-Q-26-018 — new job created.

Brad Sherriff — Full Aero Package (Time Attack)

CNC Active Bespoke

Contract value

$32,000

Est. cost

$12,800

Margin

60%

Due

10 Oct 2026

Customer

Brad Sherriff Racing

Owner

Tom R

Qty

1

Station

CNC

Splitter, wing, diffuser + mounts.

Pre-machining design check

Verified against the mould / chassis jig before any carbon is cut.

All pass
CheckNominalActualTolResult
Wing pillar bolt patternOK. 120.0 mm 120.0 mm ±0.3 mm Pass
Diffuser strake spacingOK. 65.0 mm 65.0 mm ±0.5 mm Pass

Materials against this job

Consumed cost $1,285
MaterialLotQtyWasteCostState
CF-TW-210P Carbon Twill 3K 210gsm Prepreg LOT-PP-2609 10 m² 0 $890 Allocated
HW-TICAP-M8 Titanium Cap Head Bolt M8 18 ea 0 $83 Allocated
CF-SATIN-193 Carbon Satin 5HS 193gsm LOT-CF-2606 6 m² 0 $312 Allocated

Workshop routing

  1. Design & ply bookDesign · 9/10h Done
  2. 2 CNC mould/patternCNC · 6/14h Active
  3. 3 Layup & debulkLayup · 0/20h Pending
  4. 4 Cure (oven)Oven · 0/8h Pending
  5. 5 Finishing & clearFinishing · 0/10h Pending
  6. 6 QA & sign-offQA · 0/4h Pending
Progress34%

Activity

No activity yet.