SC
3

Notifications

Design check on hold

ANU Solar tub — roll-hoop pitch 7.5 mm short. Cutting blocked until resolved.

Invoice overdue

SC-INV-10680 (Tilton) is 19 days overdue — $7,480.

5 materials below reorder

Prepreg twill, forged tow, Nomex 6mm, vac bag film, threaded pucks.

Job due soon

SC-J-26-0146 (Evo bonnet) due 18 Sep — in QA.

Prepreg out-life

Film adhesive LOT-AD-2555 expires 18 Oct — use or quarantine.

Batch certified

SC-J-26-0169 complete — 12 strakes serialised, COC issued.

PO received

SC-PO-26-044 received — bagging consumables back in stock.

Quote accepted

Xtreme Motorsport accepted SC-Q-26-018 — new job created.

Xtreme GTR — Front Splitter, Canards & End Plates (WTAC 2026)

Layup Active Bespoke

Contract value

$18,500

Est. cost

$7,200

Margin

61%

Due

02 Oct 2026

Customer

Xtreme Motorsport

Owner

Dylan M

Qty

1

Station

Layup Bay 2

Full front aero package for WTAC Pro campaign.

Pre-machining design check

Verified against the mould / chassis jig before any carbon is cut.

All pass
CheckNominalActualTolResult
Splitter leading-edge radiusMatches mould. 6.0 mm 6.0 mm ±0.5 mm Pass
Canard mount hole pitchOK. 88.0 mm 88.0 mm ±0.3 mm Pass

Materials against this job

Consumed cost $1,939
MaterialLotQtyWasteCostState
CF-TW-210P Carbon Twill 3K 210gsm Prepreg LOT-PP-2609 14 m² 1.8 $1,246 Drawn
CF-SATIN-193 Carbon Satin 5HS 193gsm LOT-CF-2606 8 m² 0.9 $416 Drawn
RES-EPX-INF Epoxy Infusion Resin LOT-RS-2610 4.5 kg 0.3 $162 Drawn
HW-TIBTN-M8 Titanium Button Head Bolt M8 24 ea 0 $115 Drawn

Workshop routing

  1. Design & ply bookDesign · 7.5/8h Done
  2. CNC mould/patternCNC · 11/10h Done
  3. 3 Layup & debulkLayup Bay 2 · 9/16h Active
  4. 4 Cure (oven)Oven · 0/6h Pending
  5. 5 Finishing & clearFinishing · 0/8h Pending
  6. 6 QA & sign-offQA · 0/3h Pending
Progress62%

Activity

Advanced to Layup — carbon & resin drawn from stock.

Dylan M · 14 Sept, 09:12 am

Design check PASS — all items within tolerance.

Tom R · 06 Sept, 11:20 am